Our presentation was this week and we mostly stressed how much testing and preparation we need to do to get ready for Maker Faire. As we watched the other groups present, we saw that many others were in the same mindset. In addition, we presented the progress that we have made since the last presentation and played a video demonstrating our controls system working in unison with the graphic user interface.

In the upcoming weeks, we will focus on embedding our controls system into the new bogies and testing the full system. As of now, there is no switch section of the track, so the bulk of our code cannot be tested. However, we have confirmation from the track team that it will be done within the next two weeks. Until then, we will prepare for testing.